Ministerial commitments aggregated across 6 countries and 4 clusters · 20 shown
48
Data points
24
Stalled · 50%
17
Partial · 35%
7
On track · 15%
Session
Commitment #
Cluster
Status
Country
LIVE
#
Commitment
Lead
Status
DJIETHKENSOMSSDDPS
InstitutionalGovernance & Coordination4 commitments
1
EN-06Strengthen participation in EAPP technical committees and maintain regional dialogue
Session II · C1 · Oct 2020 · Institutional
Governments, Utilities
On Track
2
EN-08Strengthen EAPP institutional organs, governance arrangements, and IRB participation
Session II · C3 · Oct 2020 · Institutional
Governments, EAPP
Stalled
3
EN-09Strengthen participation in EAPP and IRB activities, including technical capacity enhancement for market operations
Session II · C4 · Oct 2020 · Institutional
Governments, DPs, EAPP
No data
4
EN-16Finalize market operator governance arrangements and institutional structure
Session IV · C2 · Jan 2026 · Institutional
EAPP, IRB
No data
OperationalTechnical Implementation3 commitments
5
EN-07Speed up compliance with EAPP inter-connection code and guidelines, and operationalize identified EAPP control areas
Session II · C2 · Oct 2020 · Operational
Utilities, EAPP
Stalled
6
EN-14Expand and strengthen regional operational coordination among utilities, including accelerating regional SCADA/EMS systems
Session III · C5 · Apr 2024 · Operational
Utilities, EAPP
Stalled
7
EN-20Accelerate and strengthen modernization, digitalization, and climate resilience of regional power systems
Session IV · C6 · Jan 2026 · Operational
Governments, DPs, EAPP
No data
CommercialMarkets & Financial Agreements4 commitments
8
EN-10Prepare for DAM participation by establishing and equipping national electricity trading units and training national traders
Session III · C1 · Apr 2024 · Commercial
Utilities, DPs, EAPP
Stalled
9
EN-11Finalize transmission pricing methodology and protocol, plus wheeling arrangements
Session III · C2 · Apr 2024 · Commercial
Utilities, EAPP, IRB
No data
10
EN-12Facilitate both bilateral and competitive power trade in EAPP
Session III · C3 · Apr 2024 · Commercial
Governments, Utilities, EAPP
Stalled
11
EN-13Strengthen commercial frameworks, market rules and settlement arrangements for regional electricity trade
Session III · C4 · Apr 2024 · Commercial
EAPP, IRB
No data
PlanningStrategy & Policy Roadmaps9 commitments
12
EN-01Prepare and implement national grid strengthening plans aligned with EAPP standards to support regional trade
Session I · C1 · Oct 2019 · Planning
National Utilities
Stalled
13
EN-02Integrate regional supply and power trade options into national power sector plans
Session I · C2 · Oct 2019 · Planning
Governments
No data
14
EN-03Strengthen regional planning coordination and expand regional power system infrastructure investments
Session I · C3 · Oct 2019 · Planning
WB / AfDB / DPs / EAPP
No data
15
EN-04Support renewable energy generation expansion through least-cost regional energy planning and implementation
Session I · C4 · Oct 2019 · Planning
Governments, Utilities, DPs
No data
16
EN-05Improve utility financial sustainability, operational efficiency, and loss reduction
Session I · C5 · Oct 2019 · Planning
Governments, Utilities
Stalled
17
EN-15Prepare investment-ready regional transmission projects and coordinate financing
Session IV · C1 · Jan 2026 · Planning
Governments, DPs
No data
18
EN-17Support Mission 300 and develop National Energy Compacts to expand energy access
Session IV · C3 · Jan 2026 · Planning
Governments
No data
19
EN-18Promote renewable energy investment, distributed solutions, and clean cooking initiatives
Session IV · C4 · Jan 2026 · Planning
Governments, DPs
No data
20
EN-19Mobilize financing and private sector investment for regional grid strengthening
Session IV · C5 · Jan 2026 · Planning
Governments, Utilities, DPs
No data